You can place a dependency between two elements in the table and planning views.

1. In table display

If you're adding from a table view, you'll need the object key of the element with which you're going to create a dependency.Right-click on the element on which you wish to place a dependency; this will open the dependency settings pop-up.Then add the dependency of your choice, previous or next, and enter the object key of the dependent element in the object key column.Once you've made your settings, click on validate.You can also do this from your roadmap, by adding the previous dependencies / next dependencies columns. Clicking on one of these columns will open the same pop-up window as above.

2.in schedule display

If you move your mouse over the bar of an element, you will see two black dots at its ends.
Click on the point of your choice (depending on whether you wish to place a previous or next dependency) and hold down the mouse button.
Then drag your mouse to the bar of the element on which you wish to place your dependency, and position yourself on the desired point at one of its ends.
Release your left mouse button and click "Ok"in your browser message to validate your dependency.

Dependencies are shown in the schedule by arrows between the various elements.


Have you found your answer?
Thank you, your opinion counts!
Oops! Something went wrong while submitting the form.

Can't find what you're looking for?

Don't worry, you can contact us at support@tabsters.fr specifying the nature of your request. Our agents will get back to you as soon as possible.
Contact us